Turkmenistan

List of Projects (Turkmenistan)

Year Name Client General information Status
2015 Construction of a booster compressor station "Malay" gas field State Concern "Turkmenneftegasstroy" Installation and piping of six Compressor Units. Active
2015 Expansion of the existing compressor station "Bagtyyarlyk" State Concern "Turkmengas" Installation and piping of one Compressor Unit. Active
2015 Assignment into the lease crane vessel "Temruk" Customer: "NCG Services" Provision of Offshore installation and transport services on LAM and Zdanov Offshore oil fields. Active
2014 Provision of pipeline coating services for Garagol Deniz Development Project General Customer: «PETRONAS Carigali Turkmenistan Sdn Bhd» Customer: «Wasco Coatings Malaysia Sdn. Bhd.» Installation of Concrete Weight Coating on piped Dia. 355,6 mm. The length of pipeline is 72 km. Completed
2013-2014 Assignment into the lease crane vessel "Temruk" “Dragon Oil” (Turkmenistan) Ltd. Provision of Offshore installation and transport services on LAM and Zdanov Offshore oil fields. Completed
2013 Modification of Gas outlet of production separator at MCR-A “PETRONAS Carigali Turkmenistan Sdn Bhd” The major activities:
    • Prefabrication and Fabrication Piping Works;
    • By Pass Service Platform (Prefabrication and Fabrication at Offshore)
Turkmenistan, Balkan Velayat. Caspian Sea shelf, Turkmenistan.
Completed
2013 Environmental projects development including waste water treatment plant construction, sewerage system and water cooling towers reconstruction at the Turkmenbashi oil processing complex “Turkmenbashi oil processing complex” The major activities associated with the engineering, procurement and "turn-key" construction:
    • industrial waste water treatment facilities for the first system with processing capacity of 900 m3/hr;
    • industrial waste water treatment facilities for the second system with processing capacity of 300 m3/hr;
    • domestic water treatment facilities with processing capacity of 26 m3/hr.
    • water cooling towers with processing capacity of 400, 500, 800 m3/hr. respectively for refinery crude oil distillation units;
    • oily sludge treatment unit with processing capacity of 2 m3/hr;
    • pressurized industrial and domestic water sewerage system with capacity of 1226 m3/hr;
    • maximum permissible discharges project for refinery;
    • maximum permissible emission project for refinery;
    • ecological passport for refinery;
    • waste placement limits project for refinery.
Turkmenistan, Balkan Velayat.
Active
2013 Construction "Beamed across the river Amu Darya Du1400mm" for second pipeline "Turkmenistan-China". State Concern “Turkmengas”
    • Design and survey work, including project appraisal, supervision
    • Supply of materials and equipment
    • Construction and installation work on the site beam transition
    • Construction and installation work on the linear part
    • Construction and installation work at home attendants
Start-up
2013 Site Surveying, Design, Engineering Services “RWE Dea AG” Site Surveying, Design, Engineering Services. Turkmenistan, Balkan Velayat. Completed
2013 Off-site facilities design and construction at the Turkmenbashi oil processing complex “Turkmenbashi oil processing complex” The major activities associated with the engineering, procurement and "turn-key" construction:
    • boiler house with steam processing capacity of 70 t/hr;
    • water treatment plant with steam processing capacity of 105 t/hr;
    • air compressed station with processing capacity of 16500 nm3/hr;
    • nitrogen generation plant with processing capacity of 1586 nm3/hr;
Turkmenistan, Balkan Velayat.
Active
2013-2014 Pipeline gathering and transportation of gas and component objects. Water intake station. Refolding of part of existing natural gas pipelines and Ø530h7mm Ø720h8mm “Chuan Qing Drilling Engineering Company Limited Turkmenistan Branch” (CCDCT) • Remove of gas pipeline DN530 and DN720, including opening the trench.
• Installation of pipelines DN530 and DN720, including trenching, welding and assembly, non-destructive testing of weld joints, laying in the trench, the inner cavity of the calibration pipeline, hydraulic testing, cleaning, filling the pipeline with nitrogen.
• Additional work - underpass pipelines through highway. Turkmenistan, Lebap velayat.
Completed

2013

Design and construction of dehydration plant "Bagtyyarlyk-2" State Concern “Turkmengas” The structure of the technological area includes the following technological facilities: - Production line for drying;
- Unit for condensate collecting;
- Flare system;
- Automatic gas distribution station Each production line with capacity of 15 mln.nm3/day consists of the following equipment:
- Adsorbers with valve blocks for each adsorber - 6 units; (capacity of each unit is 3.5 mln.nm3/day);
- Furnace blocks: valve block for fuel lines, valve block for product lines, valve block for metering lines - 1 unit;- Gas cooler - 1 unit;
- Separator unit - 1 unit;
- Filter unit - 1 unit;
- Block buffer tank division - 1 unit;
- Gas metering unit - 1 unit.
Start-up

2013

Engineering, Procurement and Construction of Fire Engine House “Burren resources Petroleum Limited” (ENI) Engineering, Procurement and Construction of Fire Engine House. Turkmenistan, Balkan Velayat. Active (on hold by Client)

2011-2012

Epic of BLOCK-4 riser platform and future risers General Customer: “Dragon Oil” (Turkmenistan) Ltd. Customer: “NCG Services”
    • Fabrication of steel structures of for two modules of Topside offshore platform BLOCK -4
    • Fabrication of steel structures of for two Boat Landing Modules for offshore platform BLOCK -4
Total weight of fabricated steel structures is 375 tn. Turkmenistan, Balkan Velayat.
Completed

2011-2012

Construction of facilities for auxiliary destination on contract territory "Hazar" on oil field "Eastern Cheleken"

State Concern “Тurkmennebit”, Operator: “Consortium Khazar”

    • Construction of a hangar for storage of chemicals (2000m2);
    • Construction of the "Material and technical resources base" including:
- Administrative building for 16 employees;
- Production and warehouse building (​​630m2 each) - 4 pcs.
- Warehouse (240m2);
- Checkpoints - 4 pcs.
- Asphalt ground area (33870m2);
- Gravel area size and 90x115m 90x100m.
    • Expanding of base camp dining room;
    • Construction of a dormitory of 30 beds - 2 pcs.
Completed
2011

Structural upgrade and piping facilities for LAM and Zhdanov Platforms

General Customer: “Dragon Oil” (Turkmenistan) Ltd. Customer: “NCG Services”
    • Fabrication of steel structures of Topside module for Additional Part for offshore platform LAM-A
    • Fabrication of steel structures of Boat Landing Module for offshore platform LAM-A
    • Fabrication of steel structures of modules for upgrading offshore platforms Zhdanov-21 and Zhdanov-60
Total weight of fabricated steel structures is 350 tn. Turkmenistan, Balkan Velayat.
Completed
2011 Construction of 1400 mm “Gas bypass pipeline “Dovletabat-Deryarlyk, II line” State Concern “Turkmengas”
    • Right-of-way clearing and dune cutting 24.6
    • Trenching and backfilling 52.46 km.
    • Pipe handling 24.6 km.
    • Gas pipeline assembling 24.6 km.
    • Welded joints quality control 24.6 km.
    • Welded joints insulation and gas pipeline installation 52.46 km.
    • Pipeline breaking liquidation 52.46 km.
    • Gas pipeline ballasting by NSM (nonwoven synthetic material) 2.3 km.
    • Gas pipeline test trial 63.3 km.
    • Cathodic protection 63.3 km.
Turkmenistan, Dashoguz velayat.
Completed
2011-2016 EPIC of Stand Alone Export Oil Treatment Facilities State Concern “Тurkmennebit”, Operator: “Consortium Khazar” According to the contract PetroGas company has committed for engineering, procurement and construction of oil treatment facilities on oilfield Eastern Cheleken, which is operated by State concern Turkmennebit. Facilities designed for treatment capacity 500-3000 cubic meter emulsion which can contain 50% water and near 1000000 cubic meter gas per day. Quality of treated oil should meet TDS/GOST 9965-76 requirement for 1 group export oil . The main points of project are:
    • Oil Storage Vertical Tank 3x5000 m3
    • AKER Oil Treatment Equipment:
Two “Slug Catcher” units, with 19 000 BPD capacity each, Fuel Gas Scrubber, Two “Heater-Treater” units, with 19 000 BPD capacity each, Degassing Boot.
    • Fuel Gas Compressor Unit 373 kW
    • Gas Turbine Power Generator 3800 kW (Solar® Turbines)
    • Two trunk line oil heaters 3400 kW
    • MVSW(6,3 kV) & LVSW(0,4 kV) Schneider Electric switchboard equipment.
    • Honeywell Distribution Control System C-300/Emergency Shutdown System
    • Welding process piping and X-ray quality control 17.2 km.
    • Gas flare system with the capacity 48,000 kg/h (Flare Ind®)
Turkmenistan, Balkan Velayat. Oilfield “Eastern Cheleken”
Completed
2010 56” Trunk gas-line Malay-Bagtyyarlyk, gas dewatering facility, accounting-measurement unit State Concern “Turkmengas” Gas dewatering facility with capacity of 21.9 billion m3/year installation on Malay-Bagtyyarlyk gas-line.
    • Gas-line part installation (scraper receiving unit).
    • Pipeline route (56”, length - 107,2 km).
    • Topographical and geological surveys of 140 km total length.
    • Hydro meteorological survey on linear section, length 184,5 km
Turkmenistan, Lebap velayat.
Completed
2010-2014 Galkynysh Gas Field Development Project. Flow lines, Trunk lines and Well Heads Construction  General Customer: “Turkmengas” Contractor-«Petrofac»
    • Construction of a 12/10/8 inch CS flow lines (total length 80 km) included preparation ROW, stringing, welding, NDT, trenching, lowering, backfilling, cleaning and gauging, hydtrotesting, dewatering, swabbing and drying, nitrogen purging/packing.        
    • Construction of a 20/24/6 inch CS , 4 inch Alloy825, 4 inch SS316 trunk lines included preparation ROW, stringing, welding, NDT, trenching, lowering, backfilling, cleaning and gauging, hydtrotesting, dewatering, swabbing and drying, intelligent and calliper pigging, nitrogen purging/packing.
    • Construction of BVSs; Crossings thru asphalt roads, railways, rivers (underground and aboveground both); pipelines approach to GTUs
    • To carry out Electrical, Instrumentation, Cathodic protection, Telecom, Mechanical scope of work related with Flow lines and Trunk lines, Wellhead construction activity.

Turkmenistan, Mary velayat,

Completed
2010 Route survey of 56” trunk gas-line Malay-Bagtyyarlyk, Gas Dewatering Facility, Accounting-Measurement Unit. General Customer: “Turkmengas” State Concern. Customer: PC “Stroytransgas” Route survey of 56” trunk gas-line Malay-Bagtyyarlyk, Gas Dewatering Facility, Accounting-Measurement Unit. Lebap velayat, Turkmenistan. Completed
2009-2013 EPIC Project – 30” trunk pipeline and 2 infield lines. “Dragon Oil” (Turkmenistan) Ltd. Dragon Oil (Turkmenistan) Ltd., operator of the existing oil field in Cheleken Contract Area, Turkmenistan, modifies the existing oil-and-gas production, transportation and refining systems. Under the modifications, Dragon Oil (Turkmenistan) Ltd. negotiated the contract with PetroGas FZE for EPIC of new 30” trunk-line and two sub-sea infield pipelines. The major activities associated with the contract include the below listed ones:
    • Installation of a new 30” trunk line connecting Block 2 platform and NPSF (length - Offshore 29 km and Onshore 10 km).
    • Installation of 4 nos. 12” Sub-sea tie-ins on the new 30” trunk line.
    • Installation of intra-field 18” Sub-sea flow line from LAM 28 platform to LAM A plat- form (length - Offshore 5 km).
    • Installation of intra-field 20” Sub-sea flow line from LAM A platform to Block 2 platform (length - Offshore 5 km).
    • Installation of Pig Launcher at LAM 28 platform and Pig Receiver at LAM A platform for 18” pipeline.
    • Installation of Pig Launcher at LAM A platform and Pig Receiver at Block 2 platform for 20” pipeline.
Installation of Pig Launcher at BLOCK-2 platform and Pig Receiver at NPSF for 30” pipeline. Caspian Sea shelf, Turkmenistan.
Completed
2008-2010 Epic for central production facilities expansion (phase II) “Dragon Oil” (Turkmenistan) Ltd. In 2008 the companies Dragon Oil (Turkmenistan) Ltd. and PetroGas FZE negotiated contract to build additional facilities of the existing plant (constructed by PetroGas FZE during 2006-2007 years) for collecting and cleaning of crude oil from wax, associated gas and water. This unit is an extension of the existing plant and increases the quality of transported oil exports and productivity of the plant to 50 000 bpd. The following major technological systems were established:
    • Three “Slug Catcher” units, with 37 500 bpd capacity each.
    • Two vertical second-stage oil de-gassing separators “Scrubber” with 220 m3 capacity.
    • Automatic water purification “Flotation Unit”, manufactured by CAMERON.
    • Two “Heater Treater” units with 25 000 bpd capacity.
    • Last stage oil de-gassing separation unit “Degassing Boot” with 75 000 bpd capacity.
    • Gas-flare for emergency flaring, 60 m high and with 1 000 000 m3 per day capacity. The gas-flare is equipped with an automatic flame-control and a pilots’ re-ignition system.
    • Condensate collecting tank and pumps, ex- hausting condensate to the existing drainage system.
Turkmenistan, Balkan velayat.
Completed
2008-2009 1400mm gas pipeline “Malay-Bagtyyarlyk” General Customer: State Concern “Turkmengas” Customer: PC “Stroytransgas” 1400mm gas pipeline “Malay-Bagtyyarlyk”, length 107,2 km. Lebap velayat, Turkmenistan. Completed
2008 Upgrade of LAM-13 and LAM-28 platform structures for Drilling Programme General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” (Turkmenistan) Ltd. Upgrade of LAM-13 and LAM-28 platform structures for Drilling Program. Caspian Sea shelf, Turkmenistan. Completed
2008 EPIC Project “Upgrade of Aladja Jetty – Phase II”. General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil “(Turkmenistan) Ltd. EPIC Project “Upgrade of Aladja Jetty – Phase II”. Hazar, Balkan velayat, Turkmenistan. Completed
2008 EPIC Project “Diesel and fresh water storage tanks with loading & unloading facilities”. General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” (Turkmenistan) Ltd. EPIC Project “Diesel and fresh water storage tanks with loading & unloading facilities”. Hazar, Balkan velayat, Turkmenistan. Completed
2008 Structural upgrade of LAM-21 and LAM-22 platforms General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” (Turkmenistan) Ltd. Structural upgrade of LAM-21 and LAM-22 platforms. Caspian Sea shelf, Turkmenistan. Completed
2008 Route survey of 40” gas pipeline “Gas terminal Kyyanly – border of Kazakhstan”. General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Petronas Charigali” Company, Malaysia Route survey of 40” gas pipeline “Gas terminal Kyyanly – border of Kazakhstan”. Balkan velayat, Turkmenistan. Completed
2007-2008 Installation works at “DKS “Dovletabad-3” object. General Customer: “Turkmengas” State Concern. Customer:

Еnex Process Engineering”, Belgium.

Installation works at “DKS “Dovletabad-3” object. Mary velayat, Turkmenistan. Completed
2007-2008 Construction-installation works at the object “Akpatlauk and Keymir fields construction”.

General Customer: “Turkmenneft” State Concern. Customer: “Еnex Process Engineering”, Belgium.

Construction-installation works at the object “Akpatlauk and Keymir fields construction”. Balkan velayat, Turkmenistan. Completed
2006-2008

Cleaning and reinstallation of underwater pipeline from LAM-22 to Block-2 (diameter 10”, length 4.5 km).

General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil“ (Turkmenistan) Ltd. Cleaning and reinstallation of underwater pipeline from LAM-22 to Block-2 (diameter 10”, length 4.5 km). Caspian Sea shelf, Turkmenistan. Completed
2006-2007 EPIC Project “Upgrade of Aladja Jetty – Phase I”. General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” "(Turkmenistan) Ltd. EPIC Project “Upgrade of Aladja Jetty – Phase I”. Hazar, Balkan velayat, Turkmenistan. Completed
2006-2007 EPIC Project “Power supply to NPF from State Grid”. General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” (Turkmenistan) Ltd. EPIC Project “Power supply to NPF from State Grid”. Hazar, Balkan velayat, Turkmenistan. Completed
2006-2007 Rebuilding of reloading pier in Ekerem port. General Customer: “Turkmenneft” State Concern. Customer: “Turkmenneft” State Concern. Rebuilding of reloading pier in Ekerem port. Balkan velayat, Turkmenistan. Completed
2006-2007 EPIC Project “Underwater pipeline between platforms LAM-13 – LAM-21, LAM-13 – LAM-22, LAM-22 – LAM-10, LAM-75 – Block-2, LAM-A – LAM-63” (diameter 8”, length 13 km). General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” (Turkmenistan) Ltd. EPIC Project “Underwater pipeline between platforms LAM-13 – LAM-21, LAM-13 – LAM-22, LAM-22 – LAM-10, LAM-75 – Block-2, LAM-A – LAM-63” (diameter 8”, length 13 km). Caspian Sea shelf, Turkmenistan. Completed
2006 Dovletabad-Derjalyk and Naip-Derjalyk gas pipelines (CAC). Over-ground beam crossings through the drainage water channel Dostluk (diameters 1420 mm and 1220 mm (5 lines), length 2.0 km and 3.2 km respectively). General Customer: “Turkmengas” State Concern. Customer: “Caspro Pipeline Service A.G”, Liechtenstein.

 

Dovletabad-Derjalyk and Naip-Derjalyk gas pipelines (CAC). Over-ground beam crossings through the drainage water channel Dostluk (diameters 1420 mm and 1220 mm (5 lines) , length 2.0 km and 3.2 km respectively). Dashoguz velayat, Turkmenistan. Completed
2006 EPIC Project “Additional tank (volume of 6400 m3) on “Karagel” tank farm”. General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” (Turkmenistan) Ltd. EPIC Project “Additional tank (volume of 6400 m3) on “Karagel” tank farm”. Hazar, Balkan velayat, Turkmenistan. Completed
2006 Diesel hydro-fining unit on TCOR (process pipelines 2” - 24”, length 53 km). General Customer: “Turkmenbashi Complex of Oil Refineries” (TCOR). Customer: “TECHNIP”, Germany. Diesel hydro-fining unit on TCOR (process pipelines 2” - 24”, length 53 km). Turkmenbashi, Balkan velayat, Turkmenistan. Completed
2005-2008 EPIC Project “Repair of LAM-10 oil-platform”. General Customer: The State Agency for Management and Use of Hydrocarbon Resources at the President of Turkmenistan. Customer: “Dragon Oil” (Turkmenistan) Ltd. EPIC Project “Repair of LAM-10 oil-platform”. Caspian Sea shelf, Turkmenistan. Completed
2005-2008 EPIC Project “Oil treating unit” composed of oil pump station, cleaning unit, tank farm, and pipelines of 8”-11 km, 16”-11 km. General Customer: “Dragon Oil” (Turkmenistan) Ltd. EPIC Project “Oil treating unit” composed of oil pump station, cleaning unit, tank farm, and pipelines of 8”-11 km, 16”-11 km. Hazar, Balkan velayat, Turkmenistan. Completed
2005 Dovletabad-Derjalyk and Naip-Derjalyk gas pipelines (CAC). Over-ground beam crossings through the drainage water channel Dostluk (diameters 1420 mm and 1220 mm (5 lines), length 2.1 km and 3.0 km respectively). General Customer: “Turkmengas” State Concern. Customer: “Caspro Pipeline Service A.G”, Liechtenstein. Dovletabad-Derjalyk and Naip-Derjalyk gas pipelines (CAC). Over-ground beam crossings through the drainage water channel Dostluk (diameters 1420 mm and 1220 mm (5 lines) , length 2.1 km and 3.0 km respectively). Dashoguz velayat, Turkmenistan. Completed
2005 Oil pipeline Korpedzhe-Balkanabat (diameter 16” and 20”, length 152 km and 20 km respectively; two oil pump stations and oil treating unit). General Customer: “Turkmenneft” State Concern. Customer: “Caspro Pipeline Service A.G”, Liechtenstein. Oil pipeline Korpedzhe-Balkanabat (diameter 16” and 20”, length 152 km and 20 km respectively; two oil pump stations and oil treating unit). Balkan velayat, Turkmenistan. Completed
2004-2005 Module compressor station “Goturdepe” (two compressor devices, power 1.5 mln. m³/day). General Customer: State Concern “Turkmenneft” Customer: “Turkmenneftegasstroy” State Concern. Module compressor station “Goturdepe” (two compressor devices, power 1.5 mln. m³/day). Balkan velayat, Turkmenistan. Completed
2004 Construction of gas drying system at “Deryalyk” compressor station (power 185 mln. m³/day). General Customer: State Concern “Turkmengas” Customer: “Enex Process Engineering”, Belgium. Construction of gas drying system at “Deryalyk” compressor station (power 185 mln. m³/day). Dashoguz velayat, Turkmenistan. Completed
2004 Construction of compressor station “Yylanly” (power 90 mln. m³/day). General Customer: State Concern “Turkmengas” Customer: “Progress Engineering”, U.A.E. Construction of compressor station “Yylanly” (power 90 mln. m³/day). Dashoguz velayat, Turkmenistan. Completed
2003 Over-ground beam crossing of gas pipeline Central Asia – Center (CAC III) through Kara-Bogaz-Gol Bay (diameter 1000 mm, length 1.4 km). General Customer: “Turkmenneftegas” State Trade Corporation. Customer: JSC “Ukrgaspromstroy”, Ukraine. Over-ground beam crossing of gas pipeline Central Asia – Center (CAC III) through Kara-Bogaz-Gol Bay (diameter 1000 mm, length 1.4 km). Balkan velayat, Turkmenistan. Completed
2003 Reconstruction of compressor stations “Belek”. General Customer: “Turkmenneftegas” State Trade Corporation. Customer: JSC “Ukrgaspromstroy”, Ukraine. Reconstruction of compressor stations “Belek”. Balkan velayat, Turkmenistan. Completed
2003 Reconstruction of gas-lift compressor station “Goturdepe”. General Customer: “Turkmenneft” State Concern. Customer: JSC “Ukrgaspromstroy”, Ukraine. Reconstruction of gas-lift compressor station “Goturdepe”. Balkan velayat, Turkmenistan. Completed
2003 Construction of gas pipeline and gas distributing station (GDS) for power plant of Balkanabad (diameter 12”, length 3.2 km). General Customer: “Balkanenergo” State Concern. Customer: Chalik Energy San. Ve Tic. AS, Istanbul, Turkey. Construction of gas pipeline and gas distributing station (GDS) for power plant of Balkanabad (diameter 12”, length 3.2 km). Balkan velayat, Turkmenistan. Completed

2002

Construction of Turkmenbashi Power Plant General Customer: State Trade Corporation “Turkmenneftegas” Customer: Chalik Energy TPS Limited, Malta Construction of Turkmenbashi 126.4 MW Power Plant. Balkan velayat, Turkmenistan. Completed